Berwick Area
3.9KW/h Solar Photovoltaic Array

16 X 245W Sharp Monocrystaline modules
1 X Diehl Ako Platinum 3800 S Inverter
Click fit mounting System
This system is expected to produce more than 2,925KW/h per annum and produce in the region of £1,600.00 worth of income and savings on electricity costs to the customer.
The cost of this system was off-set by the customer requiring roofing work, GMC were able to provide all services required.


The picture below shows the mounting system in place ready to recive the Sharp 245 Modules.
The slate hooks are fixed through the sarken into the rafters . GMC fit Slate air vents for the Solar cabling to penetrate the roof.
When re-roofing GMC tradesmen have marked out the array coverage and re-slated the short fall of new slates below the so the different colour slate will not be seen.

Testimonial from the Customer
"The PV array was professionally installed at a sensible no nonsence price by GMC contractors in double quick time. Whatsmore, with the 'Feed in Tariff' it represents the best possible financial investment available at this time allowing me to enjoy unrivalled returns on my investment while doing my bit for the environment at the same time. It's win win all the way and I don't say that very often!"
With regards performance to date, May has produced 545Kwh of electricity which is actually less than April despite the sun being higher. Only had one full sun day in May! Exceptionally sunny April made nearly 600 Kwh. Total from 10th March to 6th June is now 1425Kwh. I reckon the half year between the spring and autumn equinox will make close to the full years predicted output leaving the the other half (winter) to make up a desirable surplus!
GMC Have sucsessfully installed over 200KW of Solar PV with over 100completed installations, from 2 panels supplying 500w upto 200 panels supplying 50KW
GMC Building Contractors
Eco Home gets planning permission and building regulations approved.
GMC Building Contractors become Sovereign approved Contractor
GMC Building Contractors have recently been approved as a registered contractor for Sovereign Chemicals.
GMC Building Contractor - The Workshop, Princes St, Spittal, Berwick upon Tweed. TD15 1Qx Tel: 01289 304409